Lawson Lane Office Campus (Sobrato)

Lawson Lane Office Campus - Side View
Land Area: 16.4 acres
Number of Stories: 5-story office buildings, 2-story commons buildings and 4-level parking garages
Occupancy Date: Phase 1 completed; Phase 2 Pending
Project Description:

This approved project consists of phased construction of an office campus development with structured and surface parking, landscaping and site improvements. Upon full build-out, the corporate campus would provide 648,116 square feet of office/commons space and 2,948 parking spaces.

Phase 1 construction was completed in 2013 and consists of two 153,450 sq.ft., five-story office buildings, a five-level parking garage with attached 17,158 sq.ft. commons building, surface parking lots, landscaping, and site improvements.

Phase 2 construction is pending. A modified development proposal was approved by the Architectural Committee on 11/7/2018, which includes a five story 244,655 square foot office building, a two story 19,175 square foot amenity building, a parking structure with two subgrade levels and six above grade levels, surface parking (979 total parking spaces) and site landscaping.

File Number:  PLN2018-13353 
Project Planner: Debby Fernandez (dfernandez@santaclaraca.gov, 408-615-2450)
Resources:  Architectural Committee Meeting (11/7/2018) Minutes