Current Projects Underway
The City of Santa Clara Water & Sewer Utilities continues to work improving and replacing aging infrastructure throughout Santa Clara. The City is committed to providing our customers with a safe and reliable supply of high-quality drinking water. Current projects are detailed below. | ||
Hydrant Flushing will occur soon in neighborhoods from Pruneridge Avenue and Homestead Road to Pomeroy Avenue and Lawrence Expressway. |
||
For general information or questions, call Water & Sewer Utilities at 408-615-2000 and select Option 2 when prompted, or email water@santaclaraca.gov. |
Water Main Replacement Project: Amethyst Drive
When
Construction Work
September 30, 2024 to December 20, 2024
7 a.m. to 5 p.m., Monday through Friday
Note: This is a projected schedule and the dates are subject to change. City crews may face delays resulting from weather conditions or needing to address unexpected events as they arise elsewhere in the City. The Project Manager will regularly maintain the Department website with updates to project status, as project milestones are reached, or if there are changes to projected end date.
What
City crews will install replacement water mains. The City will perform this critical work to replace aging water infrastructure for a new 2,350 feet of water main. At the conclusion of water main construction, City utility crews will transfer all existing water services from the former water main to the newly installed water main. This effort will require a brief shutdown of water services. Affected customers will be contacted by City staff at least 24 hours in advance of any disruptions to coordinate and minimize inconvenience. Existing fire hydrants will be replaced in new locations as necessary.
Following the completion of the Water and Sewer Utility Department’s work for this project, the City Street Maintenance Division or approved City contractors will repair all asphalt and concrete cuts made in any of the affected streets. Temporary pavement will be periodically maintained until permanent pavement is installed. Please contact the Water and Sewer Utility Department at 408-615-2000 or WATER@santaclaraca.gov should vehicular or pedestrian traffic be impacted by temporary pavement conditions. We ask for your patience and cooperation, and request that you bear with us during this period of construction. After services are transferred, the existing system will be disconnected and the existing fire hydrants and valves may be removed.
Location
The work is located on Amethyst Drive between Glade Drive and Chromite Drive. See project location map below.
What to Expect
Traffic Impacts
- Residents will have full access to and from their driveways
- Street parking and access will be restricted between 7 a.m. and 5 p.m., Monday - Friday
- Expect traffic disruptions between the intersections of Amethyst Drive and Glade Drive, Meadowbrook Drive, & Chromite Drive
- Temporary Parking Restriction: Parking on either side of Amethyst Drive may be prohibited within and adjacent to the work area
- Follow road closure, detours, and no parking signage
- Emergency vehicles will have access 24/7
- Temporary Pavement: After the water main construction is complete, will install temporary pavement until the final pavement restoration can be scheduled. Temporary pavement conditions may impact the vehicular and pedestrian traffic and we ask for your patience and cooperation during this period of construction.
Temporary Shutdown of Water
- Near the beginning of construction, City crews will connect to the existing water main which will require a shutdown of water (may take up to 8 hours)
- During the last stages, City crews will transfer existing water services from the existing water main to the new water main which will require a shutdown of water (approximately 1 hour)
- Residents within the project site area will be notified at least 24 hours in advance of any water service shutdown by flyer notification, door hanger or by phone
Location of New Water Main Replacement
Water Main Replacement Project: Borax Drive
When
Construction Work
July 15, 2024 to October 20, 2024
7 a.m. to 5 p.m., Monday through Friday
Note: This is a projected schedule and the dates are subject to change. City crews may face delays resulting from weather conditions or needing to address unexpected events as they arise elsewhere in the City. The Project Manager will regularly maintain the Department website with updates to project status, as project milestones are reached, or if there are changes to projected end date.
What
City crews will install replacement water mains. The City will perform this critical work to replace aging water infrastructure for a new 2,140 feet of water main. At the conclusion of water main construction, City utility crews will transfer all existing water services from the former water main to the newly installed water main. This effort will require a brief shutdown of water services. Affected customers will be contacted by City staff at least 24 hours in advance of any disruptions to coordinate and minimize inconvenience. Existing fire hydrants will be replaced in new locations as necessary.
Following the completion of the Water and Sewer Utility Department’s work for this project, the City Street Maintenance Division or approved City contractors will repair all asphalt and concrete cuts made in any of the affected streets. Temporary pavement will be periodically maintained until permanent pavement is installed. Please contact the Water and Sewer Utility Department at (408) 615-2000 or WATER@santaclaraca.gov should vehicular or pedestrian traffic be impacted by temporary pavement conditions. We ask for your patience and cooperation, and request that you bear with us during this period of construction. After services are transferred, the existing system will be disconnected and the existing fire hydrants and valves may be removed.
Location
The work is located on Borax Drive between Glade Drive and Chromite Drive. See project location map below.
What to Expect
Traffic Impacts
- Residents will have full access to and from their driveways
- Street parking and access will be restricted between 7 a.m. and 5 p.m., Monday - Friday
- Expect traffic disruptions between the intersections of Borax Drive and Glade Drive, Meadowbrook Drive, & Chromite Drive
- Temporary Parking Restriction: Parking on either side of Borax Drive may be prohibited within and adjacent to the work area
- Follow road closure, detours, and no parking signage
- Emergency vehicles will have access 24/7
- Temporary Pavement: After the water main construction is complete, will install temporary pavement until the final pavement restoration can be scheduled. Temporary pavement conditions may impact the vehicular and pedestrian traffic and we ask for your patience and cooperation during this period of construction.
Temporary Shutdown of Water
- Near the beginning of construction, City crews will connect to the existing water main which will require a shutdown of water (may take up to 8 hours)
- During the last stages, City crews will transfer existing water services from the existing water main to the new water main which will require a shutdown of water (approximately 1 hour)
- Residents within the project site area will be notified at least 24 hours in advance of any water service shutdown by flyer notification, door hanger or by phone
Location of New Water Main Replacement
Water Main Replacement Project: Crystal Drive
Update – September 24, 2024
The installation of the new water main and water service transfers have been completed. Permanent pavement will be performed by the City’s Streets Department or approved City contractors.
Temporary Parking Restriction: Parking on either side of Crystal Drive may be prohibited within and adjacent to the work area.
Temporary Pavement: After the water main construction is complete, will install temporary pavement until the final pavement restoration can be scheduled. Temporary pavement conditions may impact the vehicular and pedestrian traffic and we ask for your patience and cooperation during this period of construction.
Location of New Water Main Replacement
Water Main Replacement Project: Meadowbrook Drive
Update – September 24, 2024
The installation of the new water main and water service transfers have been completed. Permanent pavement will be performed by the City’s Streets Department or approved City contractors.
Temporary Parking Restriction: Parking on either side of Meadowbrook Drive may be prohibited within and adjacent to the work area.
Temporary Pavement: After the water main construction is complete, will install temporary pavement until the final pavement restoration can be scheduled. Temporary pavement conditions may impact the vehicular and pedestrian traffic and we ask for your patience and cooperation during this period of construction.
Location of New Water Main Replacement
Water Main Replacement Project: Agate Drive
Update – September 24, 2024
The installation of the new water main and water service transfers have been completed for Agate Drive between Glade Drive and Meadowbrook Drive. A portion of the existing main along Agate Drive between Meadowbrook Drive and Moraine Drive will be kept in service to supply water to other portions of the neighborhood until water main construction for Crystal Drive, Borax Drive, and Amethyst Drive is completed. After that, City crews will install new water main between Meadowbrook Drive and Moraine Drive and transfer the remaining water services. This is expected to be completed by the end of 2024.
The City’s Streets division or an approved City contractor will be installing permanent pavement shortly after the water construction is completed.
What to Expect
Traffic Impacts
- Residents will have full access to and from their driveways
- Street parking and access will be restricted between 7 a.m. and 5 p.m., Monday - Friday
- Expect traffic disruptions between the intersections of Agate Drive & Glade Drive, Meadowbrook Drive, and Moraine Drive
- Temporary Parking Restriction: Parking on either side of Agate Drive, Icefield Court, and Landslide Court may be prohibited within and adjacent to the work area
- Follow road closure, detours, and no parking signage
- Emergency vehicles will have access 24/7
- Temporary Pavement: After the water main construction is complete, will install temporary pavement until the final pavement restoration can be scheduled. Temporary pavement conditions may impact the vehicular and pedestrian traffic and we ask for your patience and cooperation during this period of construction.
Temporary Shutdown of Water
- Near the beginning of construction, City crews will connect to the existing water main which will require a shutdown of water (may take up to 8 hours)
- During the last stages, City crews will transfer existing water services from the existing water main to the new water main which will require a shutdown of water (approximately 1 hour)
- Residents within the project site area will be notified at least 24 hours in advance of any water service shutdown by flyer notification, door hanger or by phone
Location of New Water Main Replacement
Water Main Replacement Project: Glade Drive
Update – September 24, 2024
The installation of the new water main and water service transfers have been completed. Permanent pavement will be performed by the City’s Streets Department or approved City contractors.
Temporary Parking Restriction: Parking on either side of Glade Drive may be prohibited within and adjacent to the work area.
Temporary Pavement: After the water main construction is complete, will install temporary pavement until the final pavement restoration can be scheduled. Temporary pavement conditions may impact the vehicular and pedestrian traffic and we ask for your patience and cooperation during this period of construction.
Location of New Water Main Replacement
Water Main Replacement Project: Chromite Drive
Update – September 24, 2024
The installation of the new water main and water service transfers have been completed. Permanent pavement will be performed by the City’s Streets Department or approved City contractors.
Temporary Parking Restriction: Parking on either side of Chromite Drive may be prohibited within and adjacent to the work area.
Temporary Pavement: After the water main construction is complete, will install temporary pavement until the final pavement restoration can be scheduled. Temporary pavement conditions may impact the vehicular and pedestrian traffic and we ask for your patience and cooperation during this period of construction.
Location of New Water Main Replacement
Well 34 Rehabilitation Project
When
Construction Work
September 18, 2023 to November 17, 2023
(dates subject to change)
7 a.m. to 5 p.m., Monday through Friday
What
The City will be rehabilitating Well 34 to improve water infrastructure reliability and service to its customers. The work will consist of cleaning the existing well screens and redevelopment of the well via pumping and surging. All work will be performed within the City owned well site property.
Location
Well 34 is located at 615 Moreland Way.
What to Expect
Traffic Impacts
- Residents will have full access to and from their driveways
- Temporary Parking Restriction: Street parking directly in front of the well site at 615 Moreland Way may be restricted between 7 a.m. and 5 p.m., Monday – Friday. The City will post temporary signage including “NO PARKING” signs and warning signs as needed
- Emergency vehicles will have access 24/7
Night Work
- Approximately one week of night work will be required and is estimated to occur towards the end of October. The project includes redevelopment of the well to mitigate sand entrainment which will require continuous pumping of the well for approximately 5 days. The noise experienced will be similar to the existing well operations. Additional notices will be provided as the work progresses and the dates for the night work are confirmed.
Location of Well 34 Rehabilitation
Not to Scale